|

Looking west down the construction corridor from the Luce
Line overpass. A lot of timber has been removed at this point, but little
earth has been moved. The old trestle is being saved - it will be put into
service about a half mile north (behind) this spot, over the old highway.

View looking northwest at the west end of track relocation,
milepost 29 on the Wayzata Sub. The track enters a curve here, and a
temporary access switch (3 panels visible at left of roadbed) will be
installed to reach the new roadbed. New rail has been dropped (bottom
right.)

Signal shack is installed at the west end of the Wayzata
siding, extending the siding by 600 feet. The track in the foreground will
be removed as soon as the new track is operational in "the groove".

The rail train at the west end of the construction area
(looking west). The temporary switch is being installed just around the
curve in the distance. The Cat is latching onto a couple of 'sticks' of
rail, then the work train pulls away and the rail falls to the roadbed.

After the sticks have been extracted the Cat comes along and
repositions the rail from the roadbed where it fell to the side of the
active line. Notice the extra width roadbed where the Cat is driving; the
second track used to be here before being ripped out in the 70's.

Once the new track was operational in the trench a rail
train was called to collect the old rail from the mainline and passing
track. A wedge-shaped sled at the end of the train prys the rails from the
ties as the train advances. At quarter mile intervals the loose rails are
cut and attached to those seen protruding from the end of the train, and
are pulled into the train for transport
|
I-394 west of the Twin
Cities narrows to a two lane road at Long Lake. The new road will follow
the BNSF tracks through town with both the track and the highway placed in
a trench. The affected area is over three miles long and involves three
highway over-passes, interchanges at each end of town, and a couple of
pedestrian bridges. The project started in 2003 and will complete in 2007.

This view is just east of the pictures below, and shows the
stockpiled rail. The roadbed begins to enter 'the groove' this side of the
Crystal Bay bridge in the distance. The bridge has been demolished except
for the span over the active line. As soon as the new track is operational
this span will be removed and the new bridge completed.

The Cat, having grabbed another pair of sticks, locks his
brakes while the rail train begins to move away, extracting another pair of
rails to add to the stockpile in the work area.

Another shot of the rail train, showing the front half of
the train. The taller car (3rd car from left) is the midpoint of the train;
the rail is anchored there so that, as the train stretches and contracts
during forward and backing operations, the rail stays centered on the flats
instead of working its way off the end.

This is the start of track work - the new west-end switch of
the Wayzata siding looking east. Ties have been set for about a quarter mile, rail has
been positioned near-by, and the spiker is ready to go to work. The
original plan was to start work at the west end of the project, but a 20'
high fill in that area is still settling. So, Plan B, start in the middle!

This was the big switchover day. The old main was cut
and is being pushed over to line up with the new main. There were a few
kinks to be worked out when I took the picture, but an hour or two later
the regulator had things looking pretty good. They ran the first trains at
10 mph until noon the next day when they raised the limit to 25 mph. This
will remain in affect until the temporary switch at the west end is removed
|

Looking west down the construction corridor as the new Luce Line
bridge is being hoisted into position. The tracks - the main and the
Wayzata siding - will eventually be placed under the left span; the highway
under the right span. The track curves to the left, with the new
roadbed entering a cut around the corner. The original track is elevated
15+ feet around that curve.

View looking southeast at the west end, with the path of the
new roadbed deep in sand. I've yet to figure out why it's built up so deep
- apparently stockpiled here to add compaction weight through the winter.
The track curves 35-40 degrees to the east, and is pretty well elevated.

The preassembled switches arrived in gondolas, along with a
number of hoppers loaded with ties. They are shown sitting on the the
Wayzata work siding just a block or two from the Wayzata depot, a National
Historic Landmark, open Wednesday and Weekend afternoons. Come visit us!

Here the rail train is moving slowly westward, and two
stocks of rail can be seen descending to the roadbed.

This view looks west from the Luce Line bridge, and shows
the initial track work. Ties have been laid for about a half mile, and rail
is stretched out on both sides. This section will be double-tracked (main
plus Wayzata siding.) The spiker is visible in the distance under a
partially-done pedestrian bridge. The existing track can be seen under the
right end of the bridge. Once the BNSF starts using the new track the old
track and embankment will be removed, and the pedestrian bridge completed.

This is what the track looks like after the rail train
passes. Here the ties, plates,
spikes, clamps and ballast await pickup. Once that is done the remaining
embankment will be removed to make room for the new road.
|